The project objective was the transformation of an unconfigured space on the ground floor of the N1 building at the Athens KAT general hospital into a state-of-the-art 30 bed Intensive Care Unit facility. In the 1.520 square meter space, 22 ICU beds, 8 isolation wards, support areas, personnel rest areas and locker rooms were configured. The electromechanical installations (air & water supply, generators, UPS, central air-conditioning unit) were installed in the basement and roof of the building.
The project was delivered within 60 days, in accordance with the contractual timetable.